Specialist temporary works design and demolition engineering consultancy with over 30 years’ experience, in the design of temporary works, complex demolition and specialist lifting equipment.
Services
Featured Case Studies
Prop Installation - Silvertown Tunnel TBM
The installation and removal of propping with tight tolerances and site constraints for the Silvertown TBM launch chamber.
Eggborough Power Station Cooling Tower - Blowdown
Blowdown demolition of eight cooling towers at a decommissioned coal fired station in North Yorkshire. These works were part of the overall demolition of Eggborough Power Station which was decommissioned in 2018.
Facade Retention – Majestic Leeds
Facade retention of a fire damaged historic building in the centre of Leeds to enable the demolition and reconstruction of the internal structure.
Post-Tensioned Demolition Churchill Way Flyover Demolition
Demolition engineering and associated temporary works design of two flyovers in central Liverpool. A highly complex project with a large number of engineering design challenges and environmental constraints.
Webinars & Recordings
Andun Engineering Consultants regularly run CPD webinars focused on the different aspects of Temporary Works and Demolition Engineering for the construction industry.
They are delivered by members of the Andun team, guest speakers and panelists.
News & Updates
Pre-Weakening for Demolition
Pre-weakening is the process of weakening an element of a structure in preparation for demolition by a pull-down or blowdown. The weakening process can involve removing elements or making cuts to weaken specific elements. Pulling down a structure is as it sounds. It is the application of a mechanical force...
Temporary Works Resources To Raise Awareness Within The Construction Industry
An important element of our work as temporary works designers and demolition engineers is raising awareness of the role of temporary works within the construction industry and associated best practice. As part of our commitment to this, we have developed and made available a vast array of temporary works and...
Decommissioning & Demolition of Offshore Platforms
The requirement for offshore platform decommissioning and demolition is rising as many ageing platforms in the North Sea approach the end of their operational life. This is highlighted by the fact that 180, of the 283 currently active oil and gas fields, are due to have ceased production by 2030,...
Types Temporary Works Used For Demolition Projects
Temporary works are an essential element of demolition projects to ensure safety and structural stability. Different types of temporary works may be required during demolition projects depending on the kind of structure and methodology utilised. Types of temporary works in demolition projects: Propping Systems Facade Retention Surface protection Debris netting...