Demolition engineering for the sequential dismantling of a large container crane adjacent to a live port terminal at Greenock Port.
Client: Peel Ports
Demolition Contractor: S Evans & Sons Demolition
Scope of Work
There was a lack of historical information for the crane, with just one available drawing that did not have any section sizes.
The brief was to survey the crane, complete a weight take off and design a dismantling sequence and stability assessments of the crane.
During a site visit, photographs and measurements were made to provide enough information to calculate the weight take off.
This data was then used to model the crane in 3D using BricsCAD which was used to determine centres of gravity.
This 3D model and the technical drawings were then used to create the dismantling sequence and lift weights for each component.
Site Constraints and Challenges
One key challenge was the short turnaround time required for delivery of the demolition engineering and sign off of the dismantling sequence. There was just over a month from the initial site visit to the issuing of the final design sequence.
The site was also a live container port, which ruled out other demolition methods such as pull downs or blow downs and required the planned dismantling sequence and lifts to take this into consideration.
Demolition Methodology – Crane Dismantling
A key design element was that the crane was stuck in an upright position.
The dismantling sequence was designed to take weight off the crane evenly to maintain stability. The sequence used controlled cuts and lifts in a specific order that maintained stability at each step.
The centre of gravity was tracked and stability re-checked after each incremental lift to ensure adequate balance was maintained in the upright position and if the center of gravity shifted outside acceptable limits, the sequence would be adjusted before proceeding further.
Project Overview
The demolition engineering and dismantling sequence was completed to meet the short timelines.
The crane was successfully dismantled over a two week period, with the dismantling taking place when the weather permitted safe lifting operations.
Additional Resources
Review our webinar recordings for more case studies and a review of temporary works engineering.
This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish.AcceptRead More
Privacy & Cookies Policy
Privacy Overview
This website uses cookies to improve your experience while you navigate through the website. Out of these, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may affect your browsing experience.
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.