Demolition of a post-tensioned railway bridge deck over the M62. Existing abutments and the central pier were retained for the replacement bridge.
Client: Murphy Group
Demolition Contractor: P.P. O’Connor
The demolition was carried out using large mechanical excavators, working in a “typewriter fashion” from both sides of the bridge towards the centre.
This method ensured the bridge’s stability throughout the process, gradually reducing the structure until it could no longer support itself. When the bridge could no longer sustain its weight, it was allowed to collapse in a controlled manner onto the containers.
This prevented debris from impacting the motorway and allowed for safer, more manageable processing of the remaining materials.
After the controlled collapse, the remaining sections of the bridge were processed while the structure rested on the abutments, central pier, and containers. All materials were then cleared from the site, ensuring the motorway could be reopened on schedule.